The base below a coker at a refinery in the Oil Sands needed to be repaired in order to stabilize the foundation. In order to perform the base repair maintenance the massive vessel needed to be lifted approximately 100 mm.
SKU: lifting-a-coker-for-base-repair-maintenance
Our experts will contact you within 24 hours.
Product Description
The base below a coker at a refinery in the Oil Sands needed to be repaired in order to stabilize the foundation. In order to perform the base repair maintenance the massive vessel needed to be lifted approximately 100 mm. Lifting a vessel weighing 600 tons, 9m in diameter and 40m tall required a solution with a high degree of safety, capable of maintaining the balance of the load throughout the lift.